Conceptual & detailed design - Sea Tech,
2019-2022
Concept author - P. Ezhov
Exterior design
- Sea Tech Studio
Chief
designers - P. Ezhov, A. Golov, A. Bondarenko
Consultants - S.Nikonov, S.Ayrapetov, G.Migeotte
Customer
- Severrechflot
Yard -
Zelenodolsk Yard (Rus), 2021-2023
Modern
high-speed passenger hydrofoil, project 03830 - representative of the Alfa line of hydrofoil
vessels (Alfa-120). Detailed design.
During
the design process, the dimensions of the vessel, its
proportions, layout, engines, equipment, etc. were
repeatedly revised to achieve the optimal result in terms of
transport efficiency and comfort
for passengers and crew.
The project was developed in close dialogue with the
Customer.
The technical design was approved by the RRR (RKO) at the
beginning of 2021. This page contains demo materials of the
classification project stage.
2021-2022 - the detailed design stage.
03/02/2021 - a solemn ceremony of laying 2 vessels was held at the Zelenodolsk Shipyard, which is part
of the Ak Bars Shipbuilding Corporation, for the
Khanty-Mansi Autonomous Okrug.
06/29/2022 - launching of ships.
11/18/2022 -
sea trials, 1st stage. |